| 🛠 Category → Bridge/Culvert | Tender No → 09/ridokap/ncb/tb/082-83/35 | 🏬 Publisher → Road Infrastructure Development Office, Kapilvastu | |
| 🔍 Type → Works (NCB) | 📅 Published → 13/07/2026 | ⏰ Deadline → 03/08/2026 (5 days left) | |
| 💰 Security → 669000.00 | 💵 Doc Fee → 5000.00 | 📍 Location → Lumbini, Kapilvastu | 📄 Envelope → Two (1S2E) |
| Download PDF | |||
Turnover
☞ Minimum average annual construction turnover of NRs 2,00,00,000 based on the best 3 years within the last 10 years.
Cash Flow
☞ Bidder must demonstrate access to financial resources of NRs 56,00,000 to meet cash-flow requirement.
Bid Capacity
☞ Bidding capacity must be equal to or more than NRs 2,40,00,000.
Similar Projects
☞ One contract for an N Type Suspension Trail Bridge with pile foundation, with a length not less than 120 m, completed or substantially completed as a Prime contractor, management contractor, or subcontractor within the last ten years.
☞ For complex works up to NRs 100 million, a single entity must have completed at least one contract with a value of at least NRs 1,05,00,000 as a Prime contractor, management contractor, or subcontractor, within the last ten years.
☞ For complex works up to NRs 100 million, in a joint venture, each partner must have completed at least one contract with a value of at least NRs 26,00,000 as a Prime contractor, management contractor, or subcontractor, within the last ten years.
☞ For complex works up to NRs 100 million, in a joint venture, one partner must have completed at least one contract with a value of at least NRs 1,05,00,000 as a Prime contractor, management contractor, or subcontractor, within the last ten years.
Key Activities
☞ Site clearance: minimum 500 m².
☞ Soil excavation: minimum 509.76 m³.
☞ Backfilling: minimum 195.93 m³.
☞ Pile Boring: minimum 336 m (Boring, providing and installing bored cast-in-situ RCC pile of 600mm diameter including Bentonite as per specification, excluding Reinforcement and Concrete).
☞ Construction of Gabion Box Size 2.0x1.0x1.0m (100mmx120mm - Hexagonal Mesh Type): minimum 50 m³.
☞ Construction of Gabion Box Size 3.0x1.0x1.0m: minimum 24 m³.
☞ Construction of Gabion Box Size 1.5x1.0x1.0m: minimum 36 m³.
☞ Construction of Gabion Box Size 3.0x1.0x0.3m: minimum 64.80 m³.
☞ Plain Mass Concrete 1:3:6: minimum 10.65 m³.
☞ Reinf. Cement Concrete 1:2:4: minimum 14.12 m³.
☞ Reinf. Cement Concrete 1:1.5:3: minimum 254.82 m³.
☞ Plum Concrete 40%: minimum 210.36 m³.
☞ Form Work: minimum 377.38 m².
☞ Drystone Masonry & Pitching: minimum 14.63 m³.
☞ Rubble Masonry 1:6: minimum 7.30 m³.
☞ Rubble Masonry 1:4: minimum 113.69 m³.
☞ Cement Plaster 1:4, 20mm thk: minimum 177.22 m².
☞ Erection of Towers: minimum 45.46 m.
☞ Hoisting of Main Cable: minimum 182.20 m.
☞ Hoist of Windti & Stabl Cable: minimum 190 pc.
☞ Erection of Walkway: minimum 182.20 m.
☞ Coaltar Application: minimum 182.20 m.
☞ Insurance: minimum 1 job.
☞ Structural Steel (Supply & Fabrication): minimum 32,057.31 kg.
☞ Reinforcement Steel (Supply & Fabrication): minimum 13,373.14 kg.
☞ Thimbles Ø 13mm (Supply of Thimbles): minimum 388 pc.
☞ Thimbles Ø 26mm (Supply of Thimbles): minimum 4 pc.
☞ Thimbles Ø 32mm (Supply of Thimbles): minimum 4 pc.
☞ Thimbles Ø 36mm (Supply of Thimbles): minimum 12 pc.
☞ Bulldog Grips Ø 13mm (Supply of Bulldog Grips): minimum 1,164 pc.
☞ Bulldog Grips Ø 26mm (Supply of Bulldog Grips): minimum 20 pc.
☞ Bulldog Grips Ø 32mm (Supply of Bulldog Grips): minimum 24 pc.
☞ Bulldog Grips Ø 36mm (Supply of Bulldog Grips): minimum 84 pc.
☞ Wiremesh Netting (Miscellaneous Supply): minimum 373.51 m².
☞ Sign Board (Miscellaneous Supply): minimum 2 pc.
☞ Bolts, Nut and Washers (Miscellaneous Supply): minimum 707.06 kg.
☞ Bolts, Nut Washers HSFG (Miscellaneous Supply): minimum 845.62 kg.
☞ 12 SWG GI Binding wire (Miscellaneous Supply): minimum 58.30 kg.
☞ Hot Dip Galvanization (Rust Prevention): minimum 29,550.33 kg.
☞ Material & Equipment (Transportation): minimum 204,200.42 kg.
☞ Wire Ropes (Transportation): minimum 13,812.64 kg.
☞ Wire Ropes Ø 13mm: minimum 2502.12 m (provided by the Employer).
☞ Wire Ropes Ø 26mm: minimum 388 m (provided by the Employer).
☞ Wire Ropes Ø 32mm: minimum 376 m (provided by the Employer).
☞ Wire Ropes Ø 36mm: minimum 1962 m (provided by the Employer).